DABASPETE PROJECT

Mining Area

Mining area of 13 acres (3 leases: 1 lease with 5 acres mine in the name of the company and another 8 acres and a newly acquired mine) in Makenahalli Village, Nelamangala Taluk

Mine Reserves

For a period of 20 years commencing from 2021.

PERMISSIONS

All permissions issued by the Government of Karnataka i.e. Safe Zone Declaration of Land, Conversion into Industrial Land, Consent for Establishment & Operation of Plant & Approval of Director of Mines Safety

Stone Cutting Unit

4-stage stone crushing and screening unit available with a capacity of 300 TPH, for production of M-Sand and Washed Sand

Production Capacity

It can produce a minimum quantity of 80,000 tons per month.

Operations

Cumulative Revenues: INR 405 crores during the life of the mine with a profit of INR 122 crores